June 15, 2015 at 2:00 PM - Bid Letting for Concession Stand Project
Agenda |
---|
1. Open and receive all bids
|
2. Record all bids submitted
Discussion:
Bennett Construction $134,263.85 proposed start date of 7-16-15, 40 days to completion.
Duncan Theiss Construction $180,892.00 proposed start date of 6-29-15, 54 days to completion.
Accept the lowest, best bid under advisement pending negotiations with apparent low bidder.
We have 30 days to accept/reject bids.
|