June 1, 2017 at 8:00 AM - Projects Committee Meeting
Agenda |
---|
1. UNFINISHED BUSINESS
Rationale:
At the May 8, 2017, Board Meeting, the following motion to table was passed by all present: Ruzicka make the motion, seconded by Clausen, to table the LPRCA Interlocal Agreement until next month and ask Dave Potter to be at Committee and Board Meeting. Dave Potter attended attend the Projects Committee Meeting and will be at the June 12th Board Meeting.
Recommended Motion(s):
*To move the tabled consideration of the LPRCA Interlocal Agreement off the table for full Board consideration Passed with a motion by Board Member #1 and a second by Board Member #2.
|
2. SWCP
Rationale:
Gottschalk reviewed the attached SWCP status report with the committee.
Attachments:
(
)
|
2.A. SWCP Application Approvals
Rationale:
Mike Chvatal small dam project:
Recommended Motion(s):
To approve $22,000 of LPNNRD assistance toward the construction of the Mike Chvatal dam Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
2.B. SWCP Payments
Rationale:
16-P-13 Dayle Alswager $ 1,000.00 Emergency Terrace Repain
Recommended Motion(s):
*To approve two SWCP cost share payments, as listed in the Projects Committee minutes, for a total of $ 6,927.76 Passed with a motion by Board Member #1 and a second by Board Member #2.
|
2.C. SWCP Cancellations
Rationale:
None presented at this time but it is anticipated that there will be some by the June Board meeting.
|
2.D. Wahoo Creek Cost Share Approvals
Rationale:
None at this time.
|
3. WATERSHEDS
|
3.A. Shell Creek
|
3.A.1. Shell Creek Environmental Enhancement Plan Implementation
Rationale:
NDEQ has verbally approved $300,000 of EPA 319 funds for completing designed Shell Creek bank stabilization projects in 2017 & 2018. Our required local match of $200,000 will come from $145,000 from the Nebraska Environmental Trust and the balance from the Bailey channel improvement project. Upon receiving a formal approved agreement from NDEQ, we will be advertising for bids on the Kramer Shell Creek Bank Stabilization project. |
3.B. Wahoo Creek Watershed
|
3.B.1. Wahoo Creek RCPP Update
Rationale:
We continue working with NRCS on an eventual RCPP agreement for completing Wahoo Creek Dam Sites 26 and 27. FYRA has submitted a $23,632.01 invoice as attached for completed contact work to update the watershed plan requirements for these sites and work on our Water Sustainability Fund application. This is the first billing under our $135,790 contract leaving $112,157.99 after payment. Since this work falls under an approved contract, no motion for payment is needed.
Attachments:
(
)
|
3.B.2. Wahoo Creek Watershed Water Quality Plan Phase II
Rationale:
As reported last month, NDEQ has verbally approved our Project Implementation Plan for Wahoo Creek's next phase. We anticipate having the funding agreement available by the June Board Meeting. Saunders County has been preparing a list of priority bridge replacement locations with road dams and will be contacting engineering firms for bids to design a group of structures.
|
4. LOWER PLATTE RIVER CORRIDOR ALLIANCE
|
4.A. LPRCA Monthly Report
Rationale:
The May 25 LPRCA quarterly meeting agenda, as attached, included review of the draft FY2018 proposed budget, Watershed Water Quality Plan, and Watershed Restoration Study. Dave Potter, LPSNRD Assistant General Manager will be present to review the agreement and proposed budget items.
Attachments:
(
)
|
4.B. LPRCA Draft Interlocal Agreement
Rationale:
LPSNRD Assistant General Manager Dave Potter was present to review the attached LPRCA draft Interlocal Agreement for committee approval consideration. At the May Board Meeting, this item was not voted on until more Board members could be present. This draft outlines how LPSNRD, PMRNRD and LPNNRD would continue to work together as the primary local LPRCA partners. This agreement identifies details on how each NRD will be actively involved in providing direction and funding to the Alliance. Each NRD will be in control of what projects and programs that they want or do not want to participate in. The committee recommended that the tabled May 8, 2017, Board motion to consider approval of the draft Interlocal Agreement be brought off the table for Board consideration.
Attachments:
(
)
|
4.C. LPRCA Planning Retreat Information
Rationale:
Attached is JEO's summary of the February 24, 2017, LPRCA planning retreat at Camp Ashland. Also included are minutes and notes from the quarterly meeting that was held in conjunction with the retreat.
Attachments:
(
)
|
5. OTHER
|
5.A. Platte Center Request for Elm Creek Bank Stabilization Project Assistance
Rationale:
LPNNRD has been assisting Platte Center over the years on stabilizing Elm Creek that cuts through the middle of the village. The village is ready to move into the next project phase to be completed in the fall of 2017 as attached. The estimated cost for reshaping and stabilizing the bank on the south side of main street to the first bank curve is $23,825.20. We have been approving 50% cost-share so our requested assistance would be $11,912.60. If approved, we would carry over $2,580 of their unused FY 2017 project funds and add an additional $9,332.60 for a total FY 2018 budget amount of $11,912.60. Mark Borchers with Platte Center was present to discuss the proposed project.
Recommended Motion(s):
*To approve 50% assistance up to $11,912.60 assistance for Platte Center's next phase of their Elm Creek Bank Stabilization Project and include this amount in our FY 2018 budget Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
5.B. Army COE Projects
Rationale:
This agenda heading will be handled by the O, E & RW Committee in the future.
|
5.B.1. Fremont GI Study
Rationale:
The update on the progress of the GI Study is outlined in the O, E, & RW Committee Minutes. Future agenda items for Fremont GI will be transferred entirely to that committee in the future.
|
5.B.2. Schuyler 205
Rationale:
Now that the Shell Creek Levee portion of the Schuyler 205 project is complete, future topics regarding the project's operation and maintenance will be handled by the O, E & RW committee.
|
5.B.2.a. Schuyler Shell Creek Levee Annual Payment Request
Rationale:
Attached is the City of Schuyler's annual assistance request for $125,000. After this payment, LPNNRD will have contributed $500,000 toward the completion of the Shell Creek Levee portion of the 205 effort. There will be one remaining assistance request to reach $600,000 that the Board previously indicated as the maximum amount to be applied toward the Shell Creek Project efforts (not including study assistance).
Recommended Motion(s):
To approve payment of Schuyler's $125,000 assistance request as outlined in the May 8, 2017 Board approved Interlocal Agreement Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
5.B.2.b. Shell Creek Levee Operation and Maintenance Interlocal Agreement with City of Schuyler
Rationale:
Attached is the signed Operation and Maintenance Interlocal Agreement with the City of Schuyler outlining LPNNRD's intended future assistance payments for the completed Shell Creek Levee and Schuyler's responsibility for providing the local operation and maintenance needs for the levee.
Attachments:
(
)
|
5.C. Shell Creek Landowner Levee Project Update
|
5.D. First Draft FY 2018 Projects Budget
Rationale:
An early version of the FY 2017 Projects Committee Budget will be reviewed.
|
5.E. Sand Creek Annual Loan Payment and Semi-Annual Interest Payment to Union Bank
Rationale:
The committee is asked to approve our Sand Creek Annual Loan Payment of $412,925 and the Semi-Annual Interest Payment on that note to Union Bank.
Recommended Motion(s):
To approve our Sand Creek project annual loan payment of $412,925 and the semi-annual interest payment of $15,545.45 to Union Bank as attached to the Projects Committee Minutes Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
5.F. Hazard Mitigation Plan Update - FEMA Grant Application
Rationale:
As many of you recall, LPNNRD has been involving with leading a District-wide Hazard Mitigation Plan for our communities and three of our counties. While we are really a year away from needing to start the plan update process, JEO has learned that while there is upcoming grant money available to update plans this next fiscal year, there may not be in a year from now. What JEO is suggesting is that we apply for 75% assistance now to begin our HMP update process in Fiscal year 2019. As part of our application, there may be an opportunity to also apply for non-structural flood protection measures for interested communities at the same time (i.e. Fremont, Schuyler). JEO will be talking with Fremont and Schuyler before the next Projects Committee Meeting and will know how interested these communities are with moving toward a non-structural flood prevention approach. At that time, we will ask to possibly move forward with applying for FEMA grant funding to update our HMP plan in FY 2019 and potentially cooperate with Fremont, Schuyler or another committee on non-structural flood damage protection.
Attachments:
(
)
|
6. WESTERN SARPY/CLEAR CREEK LEVEE REPORT
Rationale:
No new information was presented.
|
7. ADJOURNMENT
Rationale:
The Projects Committee adjourned at 10:00 a.m.
|