February 1, 2018 at 8:00 AM - Projects Committee Meeting
Agenda |
---|
1. Selection of Chair & Vice-Chair
Rationale:
It is the time of year to select committee Chairs and Vice-Chairs. Terry Sobota is eligible to fill another year of a two year consecutive term. Don Veskerna is the Vice-Chair. Committee recommendation is requested.
Recommended Motion(s):
*To appoint Matt Bailey as Projects Committee Chair Passed with a motion by Board Member #1 and a second by Board Member #2.
Recommended Motion(s) #2:
*To appoint Don Veskerna as Projects Committee Vice-Chair Passed with a motion by Board Member #1 and a second by Board Member #2.
|
2. UNFINISHED BUSINESS
Rationale:
There is no unfinished business to address.
|
3. SWCP
Rationale:
Sean Elliott reviewed the present status of the SWCP funds.
Discussion:
Attached is current SWCP allocation spreadsheet.
Attachments:
(
)
|
3.A. SWCP Application Approvals
Rationale:
None
|
3.B. SWCP Payments
Rationale:
17-B-20 - JAMIE YINDRICK - WASCOB w/ TO: $12,500.00
17-C-16 - RANDY BRABEC - Grass waterway: $2187.78 Total SWCP claim: $14,687.78
Recommended Motion(s):
*To approve SWCP payments to Jamie Yindrick, $12,500 and Randy Brabec, $2187.78 as shown in the Projects Committee Minutes Passed with a motion by Board Member #1 and a second by Board Member #2.
|
3.C. SWCP Cancellations
Rationale:
None
|
3.D. Wahoo Creek Cost Share Approvals
Rationale:
Elliott was contacted by Gregg Fujan on 1/10/18 about receiving Lands For Conservation funding for a summer project he completed in 2017. This project was not completed until second week of October partially due to wet weather/field conditions and also due to participant unwilling to destroy small amount of crop in order to complete earthwork. Prior to construction Mr. Fujan was informed of NRD's LFC stipulations about completing work by 9/15.
Of the 16 LFC projects completed last year 6 had to lose crops in order to allow for construction. Mr. Fujan's total acreage set aside was ~4 acres and amount of cropped ground needed to complete construction by 9/15 was ~0.4 acres. Attached is a letter from Mr. Fujan.
Recommended Motion(s):
*To not approve the Lands for Conservation payment request from Gregg Fujan because of not following program requirements as presented in the Projects Committee Minutes Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
3.E. Approval of 2018 Cost Share Docket and LFC Rate
Rationale:
Attached are two documents for review and approval, synopsis below:
Recommended Motion(s):
*To approve the 2018 DNR Practice Cost List for SWCP cost share payments and the Lands for Conservation payment rate as attached to the Projects Committee Minutes Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
4. WATERSHEDS
|
4.A. Shell Creek
|
4.A.1. Shell Creek Watershed Environmental Enhancement Plan Implementation
Rationale:
We have received an $4,963.10 invoice from Larry Formanek for a septic tank replacement in the Shell Creek Watershed. Mr. Fomanek is eligible for 60% of the total eligible costs (up to a $3,000 maximum payment) minus the $200 Nebraska registration fee: ($4,963.10 - $200 x 60% = $2,857.86). Shell Creek grant funding will be used toward this payment.
Recommended Motion(s):
*To pay Larry Fomanek $2,857.86 cost share for a septic tank replacement in the Shell Creek Watershed as shown in the Projects Committee Minutes Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
4.A.2. Kramer Shell Creek Bank Stabilization Project Update
Rationale:
As reported last month, the Kramer Shell Creek Bank Stabilization Project is complete. The Board previously authorized working with Mainelli, Wagner & Associates for project bidding, staking, and construction inspection services since they completed the project design. Attached is their invoice, totaling $12,340.04, for staking the project, pre-construction meeting, and construction inspection of grading, rock placement, seeding and erosion control. This payment will come out of banked Shell Creek grant funds LPNNRD received from the Shell Creek Watershed Improvement Group and the Prairie Land RC&D. There will be approximately $13,000 of these banked funds remaining after this payment.
Recommended Motion(s):
To pay Mainelli Wagner & Associates $12,340.04, for staking, a pre-construction meeting, and construction inspection for the Kramer Shell Creek Bank Stabilization Project, as attached to the Projects Committee Minutes Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
(
)
|
4.A.3. Hamata-Vavrecek Shell Creek Bank Stabilization Project Update
Rationale:
As authorized by the Board, Assistant Manager Mountford contacted Mainelli Wagner and Associates on starting the process for completing the next Shell Creek Bank Stabilization Project (Hamata-Vavrecek) as a contract extension to the completed Kramer stabilization project. The contractor, Kohl Construction, has indicated an interest a contract extension and NDEQ has indicated that this will be allowable with regard to use 319 grant funding as a project extension. Director Bailey has also been very involved working with Colfax County to get their participation with the project and it looks promising that they will provide the engineering, permitting and construction oversight if LPNNRD provides the construction costs. While it is not yet know what the construction costs will be, they are roughly guesstimated at $100,000 at this time. The actual cost estimate is expected to be completed soon. NDEQ grant funds would be used to cover 100% of the construction cost. While we were not quite ready for a committee recommendation, there is a possibility that we may have enough details by the February 12 Board meeting for a motion to proceed. |
4.B. Wahoo Creek Watershed
|
4.B.1. Wahoo Creek Sites 26 & 27 - FYRA Planning Invoices
Rationale:
We received the attached $13,821.25 invoice from FYRA for work completed under contract to complete the Wahoo Creek Plan for Sites 26 & 27. Per Board policy, since the work is under an approved contract, no Board motion for payment is required. After this payment, $92,569.68 will have been paid on our $135,790 contract ($43,220.32 remains).
|
5. LOWER PLATTE RIVER CORRIDOR ALLIANCE
Rationale:
Existing LPRCA members have discussed the possibility of keeping the LPRCA functioning at some compactly because of the potential advantages of having a unified group of local and state entities to address future important river issues. It was also discussed that it would be time consuming to reestablish the group if disbanded. It is unknown if or how the Alliance would continue if the members would decide to stay together. LPNNRD removed itself as a member on June 12, 2017.
|
6. OTHER
|
6.A. Projects/Land Treatment Financial Statement Update
Rationale:
As of the last financial report received November 30, 2017, we had expended 24.84% of budgeted projects expenditures and 22.03% of budgeted land treatment expenditures.
|
6.B. Woodcliff Platte River Bank Stabilization Project Update
Rationale:
Attached are pictures of the Woodcliff Platte River Bank Stabilization Project that was inspected by Heimann, Elliott and Mountford with John Peterson, JEO, on January 25, 2018. The work has been going well with about 35% completed. LPNNRD has committed $300,000 ( to be paid over four years) toward the project. We have $75,000 for our first payment budgeted this fiscal year which will be paid after all work is done.
Attachments:
(
)
|
7. ADJOURNMENT
Rationale:
The Projects Committee adjourned at 9:20 a.m.
|