January 6, 2026 at 7:30 AM - Projects Committee Meeting
| Agenda |
|---|
|
1. UNFINISHED BUSINESS
|
|
2. SWCP
Rationale:
Adam Brockman, NRD Resources Technician, will be available to update on status of SWCP projects.
|
|
2.A. SWCP Application Approvals
|
|
2.B. SWCP Payments
|
|
2.C. SWCP Cancellations
|
|
2.D. Wahoo Creek Cost Share Approvals
|
|
3. JOINT WATER MANAGEMENT ADVISORY BOARD (JWMAB)
Rationale:
Dodge County is hosting training on the Incident Command System for administrators and elected officials on January 15th, 6:30pm-8:30pm. NRD staff and directors are invited (flyer attached). It is free to attend but need to be registered by the 9th. Dodge County and City of Fremont officials plan to discuss JWMAB and path forward during/after this training.
John Petersen and Kevin Kruse with JEO plan to give a brief presentation and project update on Rawhide WFPO and East Fremont Drainage project at the March 9th Board Meeting.
Attachments:
()
|
|
3.A. East Fremont/Elkhorn Township Drainage - FEMA HMPG
|
|
3.B. West Fremont - FEMA BRIC
|
|
3.C. Rawhide Creek Watershed - NRCS WFPO
|
|
3.D. North Bend Drainage District
|
|
3.E. Cotterell Diking and Drainage District
|
|
4. SHELL CREEK WATERSHED
|
|
4.A. Shell Creek Implementation - 319 & NET
Rationale:
Our SCWIG NET grant application was not recommended for funding by the NET scoring committee. Final funding decisions will be made at their January 8th meeting.
The next SCWIG meeting is January 20th, 10:00am, Columbus NRCS office. Bill submitted two completed cover crop projects and two completed septic upgrades:
Recommended Motion(s):
Approve listed cost share payments totaling $27,582.47 Passed with a motion by Board Member #1 and a second by Board Member #2.
Recommended Motion(s) #2:
Proceed with bidding once permits are received. Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
()
|
|
5. WAHOO CREEK WATERSHED
|
|
5.A. Construction Update
Rationale:
The weather has been more cooperative over the last month and construction activities have kept up, highlights from the month:
Olsson weekly write - up (12/27) attached Pictures attached: 27 riser, 27 drawdown inlet, 27 riprap, 26A embankment, 26A riser - outlet
Attachments:
()
|
|
5.B. Dam Site Planning Update
|
|
5.B.1. Design - Olsson
Rationale:
Olsson continues to work through final designs with NRCS/DWEE. We expect to have DWEE permits within the next couple months for sites 84 & 55. Site 77 is still under NRCS National Watershed review.
Our ACOE 404 permit is under partner agency (NEGP, FWS) review for biological assessment revisions. Their is a new project manager at ACOE that will be reviewing our permit and she is currently being brought up to speed.
Attachments:
()
|
|
5.B.2. Real Estate - Olsson & Great Plains Appraisal
Rationale:
We expect to have sites 66 & 86 appraisals at our 1/12 Board meeting.
Updates on remaining acquisitions on sites 77, 84, 85 Danielle Allen and Cody Gerdes will be available at Board meeting for updates. Great Plains Appraisal bills attached.
Attachments:
()
|
|
5.B.3. Funding - NRCS WFPO & NeDNR JEDI
|
|
5.C. Water Quality - NWQI & 319
Rationale:
We have put in a Notice of Interest for the Wahoo Creek Implementation Project and will be submitting the Project Implementation Plan once that Notice is accepted.
We are currently working on a mailing list for the 2026 round of NWQI mailings to be sent out this spring. We have also been in contact with coops to discuss different practices they can have producers apply for. |
|
6. LOWER PLATTE RIVER CORRIDOR ALLIANCE
Rationale:
The Alliance held a meeting on December 19th at the LPNNRD. The agenda is attached. Matt Moser with USGS gave an update on continuous water-quality data loggers and the trend analysis work. Preliminary results were presented regarding trends for: water temperature, specific conductance, dissolved oxygen, nitrate, and turbidity/suspended sediment. They are also updating surrogate equations to include up to seven additional parameters. The report is expected to be published within a year, and we will ask Matt to give an update at a future Board meeting. The Alliance plans to send letters to communities letting them know that they are eligible to apply for Section 319 grant funds utilizing the Alliance's Water Quality Management Plan. LPN priority areas include two watersheds; the Headwaters of Bone Creek and the Headwaters of Skull Creek. Conceptually, if the NRD were to pursue Section 319 grant funding, practices would be similar to Shell Creek. Also discussed was the need to submit another funding request letter for the 'Lower Platte River Aquatic Ecosystem Restoration Comprehensive Study' (last year's request is attached). Also attached is an invoice for annual dues, real-time water quality monitoring, and trend analysis - will be paid via previously approved joint funding agreement.
Attachments:
()
|
|
7. MORSE BLUFF FLOOD REDUCTION
Rationale:
Staff are working with Manielli Wagner to answer questions from DWEE so they can prepare a funding agreement.
|
|
8. LESHARA DRAINAGE IMPROVEMENT
|
|
9. EROSION AND SEDIMENT RULES AND REGULATIONS
|
|
10. HAZARD MITIGATION PLAN UPDATE
Rationale:
As of 12/30, there were approximately 30 jurisdictions (attached) that need to adopt the HMP that was approved by FEMA on August 22, 2025. JEO recently sent out another reminder to these jurisdictions.
Attachments:
()
|
|
11. OTHER
|
|
12. ADJOURNMENT
|