Rationale:  1.  The committee reviewed bid proposals for the preschool stair tower project.  The project was estimated at $35,000 prior to bidding.  When the bids came in too high, the board recommended rejecting all bids and direct the architect to change the scope and materials used in the project that drove the bids too high. 


Company Base Bid Substantlly Complete Bonds Included Total Bid
Lacey Construction, Inc. 12:54 PM $155,000.00 160 Calendar Days 5.00% $155,000.00
BD Construction, Inc. 12:48 PM $123,000.00 180 Calendar Days 5.00% $123,000.00
Bierman Contracting, Inc. 12:52 PM $155,800.00 135 Calendar Days 5.00% $155,800.00