May 1, 2012 at 7:30 AM - Building Committee Meeting
Minutes |
---|
1. Attendance
Discussion:
Also in attendance were Don Hague and Brian Sweeney.
|
2. Rain Delay Letter
Discussion:
The committee discussed a letter from Anderson & Shaw Construction to Architect Ryan Stearns regarding a rain delay of approximately 16 to 17 days. Final completion is expected at the end of June or beginning of July.
Attachments:
(
)
|
3. Recommendation to Approve Payment to Anderson & Shaw
Discussion:
The committee reviewed application for payment #12 from Anderson & Shaw Construction.
Attachments:
(
)
|
4. Site Tour
Discussion:
Sweeney, Hague, Peters and Miles took a tour of the facility.
|
5. Old Business
|
5.1. Lincoln Change Order Summary/Budget
Discussion:
Sweeney reviewed and approved the latest change order requests in detail with the committee.
Attachments:
(
)
|
6. Adjournment
|