July 2, 2026 at 8:30 AM - Operations Committee Meeting
| Agenda | ||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
1. UNFINISHED BUSINESS
Rationale:
There is nothing for unfinished business.
|
||||||||||||||||||||||||
|
2. WILD NE AND OTHER PROGRAMS
Rationale:
Nothing to report.
|
||||||||||||||||||||||||
|
3. OPERATION & MAINTENANCE & OTHER ITEMS
Rationale:
The O & M staff have been doing dam inspections and maintenance, located septic tanks for the Wanahoo shower building, of which four were pumped, cutting & spraying trees, and mowing.
|
||||||||||||||||||||||||
|
3.A. Rehabilitation of Cottonwood 21-A, NRCS, HDR
Rationale:
HDR has developed the following:
1) Public Information Meeting Outreach Plan — this contains the press release, public notice, and social media text for the meeting (as well as other information for meeting logistics) 2) Draft handout for a public meeting, When the Supplemental Plan - Environmental Assessment is completed, we will set a public meeting date and advertise. Staff have prepared a draft RFP for the design phase, which the NRCS has reviewed, and we are ready to go to bid once the Supplemental Watershed Plan-Environmental Assessment is completed. FYI, We are also planning to go to construction bids for additional Wahoo Creek Watershed structures and a Watershed Plan-EA for Skull & Bone Creek. More discussion and a decision on timing is expected in the Executive Committee. Total procurement is a two-month process. |
||||||||||||||||||||||||
|
3.B. Wanahoo Basin Damage & Repair, FEMA, & Houston Engineering
Rationale:
We have not been updated by Houston Engineering on any progress with FEMA.
|
||||||||||||||||||||||||
|
3.C. WSCC Levee System: Guard Camp Turner Lake Culvert
Rationale:
The Turner Lake 48"culvert/sluice gate on the Clear Creek Levee System located in the National Guard Camp needs to be repositioned (see attachment for location). This is a Corps of Engineers design that was put in incorrectly. This was paid for by the COE and the three NRD's at a 65/35 cost-share respectively. The culvert is 2' too low and needs to be repositioned 2' higher. This has been talked about for 4+ years and the COE claims they don't have any funds to correct the mistake. They assisted with technical assistance drawings and quantities.
We are working with the National Guard and Papio NRD (LIndy Rogers, P.E.) for scheduling, advertising, and preparing bid packets. This will be funded by 150K from the National Guard and remaining NRDF Funds at approximately 344K which is a 60/40 match. The National Guard may also come up with extra unspent funds nationally. To be reimbursed by the National Guard, we will need an interlocal agreement between us and the Guard if the bid surpasses 494K.
Recommended Motion(s):
To proceed with plans to advertise for construction bids to reposition the Turner Lake culvert on the Clear Creek Levee within the National Guard Camp and to develop an interlocal agreement between the District and the National Guard for transferring funds Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
()
|
||||||||||||||||||||||||
|
3.D. Clear Creek D & D Rock Reimbursement
Rationale:
At the January board meeting, we approved cost sharing 50% with the Clear Creek D & D to rock a portion of the surface road of the Clear Creek levee. Clear Creek submitted an invoice for $10,412.65, fifty percent is $5,206.33.
Recommended Motion(s):
To cost share with Clear Creek D & D 50% which is $5,206.33, for rocking a portion of the surface road of the Clear Creek levee Passed with a motion by Board Member #1 and a second by Board Member #2.
|
||||||||||||||||||||||||
|
3.E. Wanahoo Hay
Rationale:
We received hay bids from Dan Kadavy and Meduna Family Farms. See the attached sheet for a list of bids.
Meduna's bid of $13/ton on Area "A" is the only bid for the area. Kadavy's bids of $51.50/ton on Area "B" and $25/ton on Area "C" are the high bids. The hay will be split 50% NRD, 50% Wildfire Relief.
Recommended Motion(s):
To accept the high bid of $13/ton from Meduna Family Farms on area "A" and bids of $51.50 and $25/ton from Dan Kadavy on areas "B" and "C" respectfully Passed with a motion by Board Member #1 and a second by Board Member #2.
Attachments:
()
|
||||||||||||||||||||||||
|
3.F. Grass Drill Revenue
Rationale:
Rezac Seed sent the District $1,707.80 and Clay Hills Ag (Platte Co.) sent $1,748.32 for grass drill rentals for the first half of the year.
|
||||||||||||||||||||||||
|
3.G. Sand/Duck Creek Site #16
Rationale:
The landowner for Sand/Duck Creek site #16 (~3 miles north of Prague, West side of Hwy 79) has requested that the NRD’s Ingress/Egress Easement be changed to what was used during construction. This will require us to rewrite the ingress/egress legal description and have Jovan draw up an agreement to be signed and filed with the county. Staff requested a quote from JEO due to their past experience with this project. Attached is a proposal from JEO.
Attachments:
()
|
||||||||||||||||||||||||
|
4. ROCK AND JETTY
Rationale:
Timberwood Homeowners Association submitted an invoice for $5,900. The work was done on the Platte River as maintenance. Our cost-share at 50% is $2,950. The Homeowners Assocition does have a 404 permit for this work.
Recommended Motion(s):
To pay Timberwood Homeowners Association fifty percent of $5,900 or $2,950 for Platte River bank maintenance Passed with a motion by Board Member #1 and a second by Board Member #2.
|
||||||||||||||||||||||||
|
5. LAKE WANAHOO
|
||||||||||||||||||||||||
|
5.A. Lake Wanahoo Permit Sales
Rationale:
For the month of May, the District received $10,024.50 in park permit revenue.
|
||||||||||||||||||||||||
|
5.B. Lake Wanahoo Camping Revenue
Rationale:
For the month of May, the District received $15,002.90 in camping revenue.
|
||||||||||||||||||||||||
|
5.C. Lake Wanahoo Concrete Projects
Rationale:
After reaching out to multiple contractors, we have received bids to complete two concrete projects around Lake Wanahoo. These include a patio with a sidewalk to renovate the fire pit area at the education building and a basketball/pickle ball court with a sidewalk next to the shower house in Lake Wanahoo campground.
The bids are as follows: ABS Construction - $22,995.00 Metro Grading Inc. - $20,550.00 Omaha Concrete Designs - $44,186.00 It is our recommendation to award the bid to Metro Grading Inc.
Recommended Motion(s):
To award the concrete projects mentioned above to Metro Grading Inc. with a bid of $20,550.00 Passed with a motion by Board Member #1 and a second by Board Member #2.
|
||||||||||||||||||||||||
|
5.D. Clint Johannes Education Building
Rationale:
The Clint Johannes Education Building at Lake Wanahoo was rented 17 times in June, with 4 NRD events. Revenue for the month was $1,375.
|
||||||||||||||||||||||||
|
6. INFORMATION AND EDUCATION
|
||||||||||||||||||||||||
|
6.A. Information
|
||||||||||||||||||||||||
|
6.A.1. Radio & eAds
Rationale:
KTIC radio ads schedule:
June: Abandoned Well cost-share July: Variances/25% Viaduct Summer newsletter release (latter half of July) Digital display ad schedule: Preparing new schedule for Summer and Fall |
||||||||||||||||||||||||
|
6.A.2. Analytics
Rationale:
Top Posts for Facebook and X during June included:
• Congressman Don Bacon visit to office and Wahoo Creek Watershed (over 1.5k on X) • NRD Camp flyer • Nocturnal Night flyer • Mud Day event • Abandoned well cost-share Facebook followers: 1,888 (up 1) X followers: 428 (up 1) At the end of May, RedThread upgraded a plug-in to the website’s search bar, creating Google-quality results scoped specifically to our site’s content. As a reminder, if you see any issues on our website, please let us know so we can get that fixed. At the end of May, RedThread upgraded a plug-in to the website's search bar, creating Google-quality results scoped specifically to our site's content. As a reminder, if you see any issues on our website, please let us know so we can get it fixed. On the LPNNRD website, top pages (besides the home page) • Lake Wanahoo • Czechland Lake • Forestry • Outdoor Recreation • Pollinator Program (Native Nook) Traffic from other sites directed to LPNNRD.org • Facebook (56) • NARD (13) • Visit Nebraska (13) • KETV (8) • Fox News from KTIC digital display ads (2)
Attachments:
()
|
||||||||||||||||||||||||
|
6.B. Education
|
||||||||||||||||||||||||
|
6.B.1. Past events
Rationale:
|
||||||||||||||||||||||||
|
6.B.2. Upcoming events
Rationale:
TBD: Wildflowers and Wine; Starry Night; |
||||||||||||||||||||||||
|
6.B.3. Fiscal Year Numbers for 2020-2026
Rationale:
|
||||||||||||||||||||||||
|
7. RURAL WATER SYSTEMS
|
||||||||||||||||||||||||
|
7.A. Colon System
Rationale:
Staff completed tri-annual lead/copper testing for the Colon RWD. Once results are available they will be sent to homeowners who cooperated in testing.
Routine monthly sampling completed, meters read, bills mailed 7/1. |
||||||||||||||||||||||||
|
7.B. Bruno System
Rationale:
Routine monthly sampling completed, meters read, bills mailed 7/1.
|
||||||||||||||||||||||||
|
7.C. Abie RWD
Rationale:
On 6/23 staff from JEO, LPNNRD staff, and representatives from the Village of Abie met to discuss JEO's study to incorporate Abie into the Bruno RWD. JEO determined that there is sufficient quantity potential to service Abie, and possible rural connections along the proposed 6" transmission main that would connect to our existing 8" main. Abie would continue to maintain their standpipe to provide consistent pressure and reserves.
The possibility of adding the Village of Prague to the system was also discussed. Prague has been flagged by DWEE/EPA for water quality due to PFAS and manganese and needs to develop a plan. The two possible solutions are: water treatment plant or connecting/developing a rural water district. The state has insinuated they are not in favor of a water treatment plant for a community of this size. There is also 75% cost reimbursement for a rural water connection. JEO developed a scenario to include Abie and Prague within the same system; that would connect to a new water tower in Bruno (operated/maintained by NRD RWD) and then service to Abie and Prague. Representatives from Abie offered to reach out to Prague to discuss the potential mutually before moving forward with meeting with NRD. Cost estimate for Abie connection to Bruno RWD: $3.6 million Cost estimate for Abie - Prague connection to Bruno RWD: $12 million Next steps will be to determine which alternative is the most feasible to both/all parties and then pursue funding options. There is funding available through the State if Prague agrees to connect. If the decision is made to connect only Abie then USDA Rural Development is the likeliest option.
Attachments:
()
|
||||||||||||||||||||||||
|
7.D. Other
|