Meeting Agenda
|
---|
1. Open Meeting
|
2. Roll Call
|
3. Items of Business
|
3.A. Consider Resolution 2024-13 Signing of the Municipal Annual Certification of Program Compliance 2024
|
3.B. Consider Change Order Number 003 from Kingery Construction Co. in the amount of $1,850.00
|
3.C. Consider the Application for Special Event Permit SE24-06 for a TJ Sokol's Halloween Party Fundraiser
|
3.D. Consider the Isis Theatre Phase Two Substantial Completion
|
3.E. Consider the Change Order COR#010 from Kingery Construction Co. in the amount of $3,343.00 for the Crete Isis
|
4. Officers' Reports
|
5. Adjournment
|
Agenda Item Details
Reload Your Meeting
|
|||
---|---|---|---|
Meeting: | August 6, 2024 at 5:00 PM - Public Works Committee Meeting | ||
Subject: |
1. Open Meeting
|
||
Rationale:
|
|||
Subject: |
2. Roll Call
|
||
Rationale:
|
|||
Subject: |
3. Items of Business
|
||
Rationale:
|
|||
Subject: |
3.A. Consider Resolution 2024-13 Signing of the Municipal Annual Certification of Program Compliance 2024
|
||
Discussion:
City Administrator, Tom Ourada, explained that it is required when we get NDOT money. These are funds that would only have to be used for road use.
|
|||
Action(s):
|
|||
Attachments:
|
|||
Subject: |
3.B. Consider Change Order Number 003 from Kingery Construction Co. in the amount of $1,850.00
|
||
Discussion:
City Administrator, Tom Ourada, discussed this is the end of the project. The change Order involved some electrical and nature work.
|
|||
Action(s):
|
|||
Attachments:
|
|||
Subject: |
3.C. Consider the Application for Special Event Permit SE24-06 for a TJ Sokol's Halloween Party Fundraiser
|
||
Discussion:
City Administrator, Tom Ourada, explained that Sokol was requesting Norman from 12th to 13th to be closed for the Halloween event. Further discussion was made about the security, wristbands and
|
|||
Action(s):
|
|||
Attachments:
|
|||
Subject: |
3.D. Consider the Isis Theatre Phase Two Substantial Completion
|
||
Discussion:
City Administrator, Tom Ourada, explained that the theater is now substantially complete.
|
|||
Action(s):
|
|||
Attachments:
|
|||
Subject: |
3.E. Consider the Change Order COR#010 from Kingery Construction Co. in the amount of $3,343.00 for the Crete Isis
|
||
Discussion:
City Administrator, Tom Ourada, discussed the work is done and the change order is for the flooring.
|
|||
Action(s):
|
|||
Attachments:
|
|||
Subject: |
4. Officers' Reports
|
||
Rationale:
|
|||
Subject: |
5. Adjournment
|